| Feature | Primavera Risk Analysis | Oracle Primavera Cloud Risk |
|---|---|---|
| Application | Desktop application (Windows) | Cloud, browser-based (SaaS) |
| Licensing | Perpetual named-user licence plus annual support | Subscription |
| Users | Single user | Multi-user, shared risk register |
| Working with Primavera P6 | ✓ Imports P6 schedules (XER) | ✓ Direct P6 EPPM integration: imports schedule and risk data, sends pessimistic dates back to P6 |
| Microsoft Project schedules | ✓ | ✓ |
| Schedule quality check | ✓ Schedule Check | ✓ Schedule Health Check |
| Risk register (qualitative and quantitative) | ✓ | ✓ Project and consolidated program registers |
| Response / mitigation planning | ✓ | ✓ Pre- and post-response analysis |
| Monte Carlo schedule and cost analysis | ✓ | ✓ |
| Weather and calendar risks | ✓ | ✓ Probabilistic weather calendar |
| Correlation | ✓ | ◐ Through risk factors |
| Probabilistic branching | ✓ | ✕ |
| Probabilistic cash flow | ✓ | ✕ |
| Sensitivity / tornado charts | ✓ | ✓ Including risk removal impact |
| Iteration analysis | ✓ | ✓ First 50 iterations with Gantt view |
| Portfolio / program level analysis | ✕ Analysis runs on a single schedule | ◐ Program-level risk register; Monte Carlo analysis runs per project |
| Dashboards, scheduled reports and notifications | ✕ | ✓ |
Oracle Primavera Cloud features are based on the Oracle Primavera Cloud Risk Management User Guide (October 2026). Primavera Cloud is updated monthly, so ask us about the latest capabilities.
Which one is right for you?
Primavera Risk Analysis
- A risk specialist runs detailed analyses on the desktop
- You need advanced modelling: probabilistic branching or probabilistic cash flow
- You already own perpetual licences
Oracle Primavera Cloud Risk
- Risks are managed by the whole project team, in the browser
- You already use Primavera Cloud, or want to connect it to P6 EPPM
- You want dashboards, notifications and a subscription model
Not sure which one fits?
We can review your projects and show both tools in a live demo.